PROGRESS REVIEW OF USF PROJECTS
The status of 3 main initiatives as on 31st August, 09:
1. Rural Telecom (RTeS) Program,
2. Broadband Program for unserved urban areas
3. Special Project - Optical Fibre Cable to all Tehsils Headquarters
1. Rural Telecom and e-Services (RTeS) Program
Under USF RTeS program contract for 10 Lots have been signed with various Service Providers. Status of these Lots is shown below;
Lot Name Operator Contract signed Total Muzas MP 1
25% MP 2
50% MP 3
75 % MP 4
100% Remarks
Malakand Telenor 4-Oct-07 1,283 Under Force Majeure
Sukkur PMCL 15-Jan-08 253 audited audited audited ready 3 milestones completed. 4th milestone in progress
DGKhan Warid 7-Feb-08 539 audited audited audited 3 milestones offered
3 milestones completed
Pishin PTCL 29-May-08 312 audited ready 2 milestone offered
1st milestone audited
Mansehra PTCL 24-Jun-08 1,479 ready 1st Milestone offered
Dadu PTCL 25-Jul-08 427 audited audited audited 3 milestones offered
1st milestone completed
Bahawalpur Telenor 22-Sep-08 888 audited audited audited ready 4 milestones offered
Audit of 4th in progress
MirpurKhas Telenor 13-Mar-09 218 1st milestone in Oct,2009
Larkana PTCL 17-May-09 72 1st milestone in Nov,2009
Nasirabad Zong 28-Jul-09 648 1st milestone in Jan, 2010
Upcoming USF telephony Lots are:
a. Khuzdar Bid Submission 29th Sept, 09
b. Kalat Bid Submission 25th Nov, 09
c. Mastung/Nushki Bid Submission 15th Jan, 10
2. USF Broadband Program
Under USF Broadband Program, so far 5 projects have been launched, three have been signed and one in progress and three are in the pipe line.
Region Name Operator Contract signed Total BB Subs MP 1
25% MP
...
...